Global Atomic Provides Update on Turkish Zinc Project

April 9, 2019

Toronto, ON, April 9, 2019: Global Atomic Corporation (“Global Atomic” or the “Company”), (TSX-V: GLO, FRANKFURT: G12) is pleased to announce an update on its BST Joint Venture Zinc Project in Iskenderun, Turkey.

Highlights:

  • The new 110,000 tonne / annum capacity Waelz kiln will be operational by August, with remaining components including the concentrate washing section to be installed in September
  • Old plant has been demolished and removed from site
  • Powerline upgrades completed allowing for expanded plant
  • Earthworks complete and new construction underway
  • 150 construction personnel currently working on site
  • Concrete forming and steelworks nearing completion
  • EAFD processing operations will be fully commissioned by the end of September, 2019
  • Please visit our website, www.globalatomiccorp.com, under “Base Metals Division” Image Gallery to see construction progress photos

 View PDF